• Consultant: C&S Engineers, Inc. 
  • Project cost:  $5.7 million 
  • Design start: March 2022 
  • Construction start: Spring 2024 
  • Construction finish: Fall 2025 

The condition of Parking lots R12 and R13 has significantly deteriorated and the below-ground infrastructure was broken and needed replacement. The project will include a full-depth reconstruction; reconfigure the parking lots for safety; replace and/or repair sidewalks and curbing; replace lighting systems; provide rain garden for storm water run-off; landscaping improvements; and add electric charging stations.