Consultant: Flynn Battaglia Architects PC
Project cost: $14.8M
Design start: April 2018
Construction start: TBD
Construction Finish: TBD
Consultant: Architectural Resources
Project cost: $78 M
Design start: January 2019
Construction start phase 1: March 2022 (Phase 1)
Construction Finish: Spring 2026 (all phases)
Consultant: TBD
Project cost: $5.2M
Design start: Spring 2021
Construction start: TBD
Construction Finish: TBD
Consultant: Kideney Architects
Project cost: $10.3M
Design start: TBD
Construction start: TBD
Construction Finish: TBD
Consultant: Kideney Architects
Project cost: $15.5M
Design start: January 2018
Construction start: TBD
Construction Finish: TBD